Acquisition Project Plan Template: M&A Integration Plan

Acquisition Project Plan Template: A Day 0 to Day 100 M&A Integration Plan

Project plan template for M&A integration

This acquisition project plan template gives you a complete, pre-filled integration plan for a business you are buying: five phases from Day 0 through Day 100, nine workstreams with named owners, a RACI matrix, a 20-row integration checklist you can paste into Excel, a risk register, and a worked synergy example with the math shown.

An acquisition project plan template is the working schedule for integrating a company you buy. It splits the work into phases (Day 0 before closing, Day 1, then Days 1 to 30, 31 to 60 and 61 to 100), lists each task by workstream with one owner, a due date and a dependency, and is reviewed weekly by an integration lead.

What an Acquisition Project Plan Template Should Include

Most templates on the first page of Google are blank spreadsheets or a list of headings. A plan you can run needs seven parts, and each one is on this page:

  1. Phases with exit tests from Day 0 to Day 100.
  2. Workstreams covering people, finance, IT, operations, customers, legal and communications.
  3. Named owners on both the buyer and target side.
  4. A RACI matrix for the decisions that cause friction.
  5. A task checklist with phase, owner, dependency and status.
  6. A risk register with warning signs and owners.
  7. A synergy tracker showing run-rate and realized cash.

Why bother with this much structure? Harvard Business Review put the failure rate of mergers and acquisitions at between 70% and 90% in a March 2011 article by Clayton Christensen, Richard Alton, Curtis Rising and Andrew Waldeck (The New M&A Playbook). A written plan does not guarantee a good outcome, but it makes problems visible while there is still time to fix them.

The Five Phases at a Glance

The table below is the spine of the plan. Every task in the checklist further down maps to one of these phases.

PhaseWindowGoalKey outputsDone when
Day 0Signing to closingPlan everything you can before you own itLeads named, Day 1 checklist, messages draftedEvery Day 1 item has an owner and a tested fallback
Day 1Closing day and the first weekNothing breaks and everyone hears the same storyAnnouncements, payroll, access, insuranceNo missed payroll, no surprised key customer
Days 1 to 30First monthStabilize people, customers and cashRetention done, key accounts called, org chartTop customers have a named owner
Days 31 to 60Second monthStart integrating the processes that create valueFirst merged close, system decisions, synergy trackerEach synergy has an owner, date and dollar figure
Days 61 to 100Third month and a bitLock in the gains and hand off to normal managementSavings banked, long projects scoped, Day 100 reviewOpen items sit with functional owners

The 100-day horizon is a planning convention, not a legal deadline. Track longer projects, such as an ERP migration, separately.

Phase-by-Phase Plan

Day 0: from signing to closing

The aim is to reach closing with no open questions about Day 1.

  • Name the integration lead and workstream leads, and agree their time commitment.
  • List change-of-control clauses from diligence and draft the consent letters.
  • Sign retention terms with the few people the business cannot lose.
  • Draft the employee announcement, manager talking points and customer and supplier letters.
  • Check whether the deal needs a Hart-Scott-Rodino filing. For 2026 the size-of-transaction threshold is $133.9 million, according to the FTC’s 2026 HSR threshold notice. If a filing is required, the FTC says the parties must wait 30 days after a complete filing (15 for a cash tender offer or bankruptcy) before closing (FTC merger review process). Ask counsel which planning steps are safe while you wait.

Day 1: closing day and the first week

Day 1 is judged on what does not go wrong. Run it from one checklist and review the issue log every evening.

  • Payroll runs on schedule, ideally on the existing payroll run for the first cycle.
  • Every employee can log in to email and the systems they use daily.
  • Insurance is bound from closing with no gap in cover.
  • Employees hear the news first, then customers and suppliers the same day.
  • Public acquirers file the SEC Form 8-K, which the SEC’s form instructions require within four business days of the triggering event.

Days 1 to 30: stabilize

  • Call every top customer and name a relationship owner for each account. Do not change prices yet.
  • Decide how to handle Form I-9 records. USCIS lets a successor employer either treat acquired staff as new hires and complete new forms, or treat them as continuing employees and keep the previous owner’s forms, in which case the buyer takes on any errors in them (USCIS guidance on mergers and acquisitions).
  • Publish the combined org chart down to manager level.
  • Set up bank accounts and signatories and start a 13-week cash forecast.
  • Send the change-of-control consent letters prepared on Day 0.

Days 31 to 60: integrate

  • Close the first full month on the buyer’s calendar, even if systems stay separate.
  • Review supplier overlap, insurance and software licenses for savings.
  • Decide keep, run in parallel or migrate for each core system.
  • Launch the synergy tracker, with a run-rate column and a realized column for every line.
  • For an asset purchase, gather the purchase price allocation inputs. The IRS says both buyer and seller file Form 8594 with their income tax return for the year of the sale when goodwill or going concern value attaches.

Days 61 to 100: optimize and hand off

  • Report the first realized savings against the deal model, line by line.
  • Scope long projects (ERP, rebrand) with their own owners and dates.
  • Run a Day 100 review with the sponsor.
  • Hand each open item to a functional owner and wind down the weekly steering meeting.

For a deeper look at the first three months on their own, see our 100-day plan after acquiring a business.

Workstreams and Owners

Each workstream needs a buyer-side lead and a target-side counterpart. In a small deal one person can lead two streams.

WorkstreamBuyer-side ownerTarget-side counterpartFirst 100 days: core deliverables
Governance (integration office)Integration leadTarget CEO or general managerMaster plan, weekly meeting, issue log
People and HRHR leadTarget HR or office managerRetention, Form I-9 approach, payroll, org chart
Finance and treasuryCFO or controllerTarget bookkeeper or controllerBanking, cash forecast, first merged close
IT and systemsIT leadTarget IT providerDay 1 access, keep or migrate decisions
Operations and suppliersOperations leadTarget operations managerSupplier notices, vendor overlap review
Customers and salesSales leadTarget owner or top account managersKey account calls, an owner per top account
Legal and complianceCounselSeller’s counselConsents, licenses, filings, HSR check
CommunicationsCommunications leadTarget CEOAnnouncements, talking points, letters
Synergy trackingIntegration lead with financeTarget controllerTracker with run-rate and realized columns

People decisions set the tone for everything else. Our guide on managing staff after an acquisition covers retention, communication and restructuring in more detail. If the seller will keep providing services after closing, document them in a transition services agreement and add each service to the plan with an end date.

RACI Matrix for the Integration

A RACI matrix stops two people from thinking they own the same decision, and stops a decision from having no owner at all. R is Responsible (does the work), A is Accountable (signs off), C is Consulted (asked before the decision) and I is Informed (told after). Keep one A per row.

Decision or deliverableDeal sponsorIntegration leadWorkstream leadTarget leaderCounsel
Approve the master plan and Day 1 checklistARCCI
Name workstream leadsARICI
Employee announcement and talking pointsACR (Comms)CC
Retention offers to key staffACR (HR)CC
Bank account and signatory changesICA/R (Finance)CI
Keep or migrate each core systemCAR (IT)CI
Change-of-control consent lettersICCCA/R
Key customer outreachCAR (Sales)RI
Synergy targets and monthly reportARCII
Layoffs or site closuresACR (HR)CR

Integration Checklist Table (Copy Into Excel)

This is the working template. Copy it into Excel, Google Sheets or your project tool, give each workstream its own tab, and add a red, amber or green status column for the weekly steering meeting.

Planning grid and sticky notes for an acquisition project plan template
#PhaseWorkstreamTaskOwnerDepends onStatus
1Day 0GovernanceName the integration lead and every workstream leadDeal sponsorNoneNot started
2Day 0GovernanceBaseline the master plan and set the weekly steering meetingIntegration leadTask 1Not started
3Day 0LegalList contracts with change-of-control or assignment clausesCounselDiligence data roomNot started
4Day 0LegalConfirm whether an HSR filing is required and track the waiting periodCounselDeal valueNot started
5Day 0PeopleAgree retention terms for key employeesHR leadDiligence people listNot started
6Day 0CommunicationsDraft employee, customer and supplier announcementsCommunications leadTask 1Not started
7Day 1PeopleConfirm payroll runs on the first scheduled dateHR leadBank detailsNot started
8Day 1ITConfirm every employee can log in to email and core systemsIT leadAccess reviewNot started
9Day 1FinanceBind insurance with no coverage gap from closingCFOBroker reviewNot started
10Day 1CommunicationsHold the all-hands and send the customer and supplier lettersCommunications leadTask 6Not started
11Days 1 to 30CustomersCall every top account and name its relationship ownerSales leadRanked account listNot started
12Days 1 to 30PeopleChoose the Form I-9 approach and publish the combined org chartHR leadTask 5Not started
13Days 1 to 30FinanceSet up bank accounts, signatories and a 13-week cash forecastControllerTask 9Not started
14Days 1 to 30LegalSend change-of-control consent lettersCounselTask 3Not started
15Days 31 to 60FinanceClose the first full month on the combined calendarControllerTask 13Not started
16Days 31 to 60OperationsReview supplier overlap and renegotiation targetsOperations leadMerged spend dataNot started
17Days 31 to 60ITDecide keep, run in parallel or migrate for each core systemIT leadSystems inventoryNot started
18Days 31 to 60SynergyLaunch the synergy tracker with run-rate and realized columnsIntegration leadDeal modelNot started
19Days 61 to 100SynergyReport first realized savings against the deal modelIntegration leadTask 18Not started
20Days 61 to 100GovernanceRun the Day 100 review and hand open items to functional ownersDeal sponsorAll streamsNot started

Add rows for anything specific to your deal, such as a facility move, a rebrand, a carve-out or a transition services agreement. Keep task names short and keep one owner per row. For what to verify once the deal has closed, use our post-close integration checklist.

Run it in a weekly steering meeting with every workstream lead, update the plan in the meeting, and give the sponsor a monthly review of the synergy tracker and top risks.

Risk Register

Rate each risk for likelihood and impact and review the top risks at every steering meeting. The ratings below are a starting point; change them to fit your deal.

RiskLikelihoodImpactEarly warning signMitigationOwner
Key employee resigns after closingMediumHighVague answers about plansRetention terms signed before closingHR lead
Top customer leaves or re-bidsMediumHighSlower orders, requests for new termsPersonal call in week one; no early price changesSales lead
Payroll or payment failure on Day 1LowHighUntested bank detailsKeep the existing payroll run for one cycleController
Counterparty uses a change-of-control clauseMediumMediumUnanswered consent letterFind clauses in diligence; send letters earlyCounsel
Rushed system migration disrupts operationsMediumHighGo-live set before data mappingRun in parallel; go live after a test closeIT lead
Synergies reported but not bankedHighMediumTracker shows run-rate onlyReport realized next to run-rate monthlyIntegration lead
Layoff triggers WARN notice dutiesLowHighSite closure plannedCheck WARN with counsel firstCounsel
Integration team burns out or stallsMediumMediumMissed meetings, stale statusProtect the lead’s time; cut low-value tasksDeal sponsor

On the layoff line: the US Department of Labor says the WARN Act requires employers with 100 or more employees to give at least 60 calendar days of written notice before a covered plant closing or mass layoff (DOL plant closings and layoffs). Several states have their own rules, so check with counsel before any announcement.

Worked Example: Tracking Synergies in a 100-Day Plan

This is an illustration, not a real deal. A buyer acquires a services business that closes on January 1. The deal model assumes $600,000 a year of cost savings from four sources. The synergy tracker records when each saving starts and what it is worth in the first calendar year.

Meeting room display tracking synergies from an acquisition project plan template
Synergy (illustrative)Annual run-rateStarts in monthMonths counted in year 1Realized in year 1
Insurance program consolidation$90,000211$82,500
Software license overlap$70,00049$52,500
Vendor consolidation$240,000310$200,000
Back-office roles not backfilled$200,00058$133,333
Total$600,000$468,333

The math for each line is the annual run-rate multiplied by the months counted, divided by 12. Insurance starts in month 2, so it counts for 11 months: $90,000 times 11 divided by 12 equals $82,500. Vendor savings start in month 3, so they count for 10 months: $240,000 times 10 divided by 12 equals $200,000.

By month 5 the tracker shows the full $600,000 run-rate, but only $468,333 lands in year 1, a gap of $131,667. If the integration costs $150,000 in one-time fees, the net year 1 benefit is $318,333. Reporting only run-rate would overstate year 1 by $131,667, which is why this template tracks both.

How CT Acquisitions Helps

CT Acquisitions is an M&A advisory firm for founder-owned businesses. We work both sides of the table: on the sell side we run confidential sales and recapitalizations for owners, and on the buy side we find, vet and negotiate acquisitions for buyers. We also run exit planning for owners who are not ready yet.

On a buy-side search we start integration planning at the letter of intent stage. How we are paid depends on the mandate, and you will know the terms in writing before any work starts.

Frequently Asked Questions

What is an acquisition project plan template?

It is the working schedule a buyer uses to combine a purchased business with its own. It lists every integration task by workstream, with one named owner, a due date keyed to Day 1 and the first 100 days, a dependency and a status reviewed weekly.

Is an acquisition plan the same as an M&A integration plan?

No. In M&A, the acquisition or integration plan is the buyer’s project plan for combining two companies. In US government contracting, an acquisition plan is a procurement document that sets out how an agency will buy goods or services, governed by Part 7 of the Federal Acquisition Regulation. This page covers the M&A meaning.

How long does M&A integration take?

Most buyers plan the intensive phase around the first 100 days after closing, which covers payroll, banking, customer outreach, the new org chart and the first synergy decisions. Longer projects, such as an ERP migration or a full rebrand, often run past Day 100 and belong in the plan as separate tracked projects.

Who should own the acquisition project plan?

One named integration lead owns the plan day to day and reports to a deal sponsor, usually the buyer’s CEO or, in a private equity deal, the deal partner or operating partner. Each workstream lead owns the tasks in their stream.

What is a RACI matrix in M&A integration?

RACI stands for Responsible, Accountable, Consulted and Informed. For each major decision it shows who does the work, who signs off, who is asked first and who is told. Keep one Accountable person per row.

Is there an acquisition project plan template in Excel?

Yes. The checklist table on this page pastes straight into Excel or Google Sheets. Give each workstream its own tab, and put the RACI matrix and risk register on tabs of their own. Smartsheet and Asana work the same way.

What should be on a Day 1 checklist after an acquisition?

At minimum: payroll runs on time, every employee can log in, payments work, insurance is in force with no gap, employees hear the news from leadership first, key customers and suppliers get a call or letter, and managers have talking points. Public acquirers also track the SEC Form 8-K deadline of four business days.

What to Do Next

Copy the checklist into a spreadsheet, put a name on every row, and book the first steering meeting before you sign. Want a second pair of eyes on the plan? A short call is a good start.

Get the integration plan right before you close.